1, hoist dismantling, the operator should check the scene with the surrounding environment, remove obstacles, delimit the danger zone and set the poles or warning signs, demolition to set up special care personnel are forbidden to enter the danger zone, and to wait the process of dismantling the frame stability, such as the discovery of tilt, immediately report for people stop working, stop measures.
2, disassembly personnel should obey the leadership, close coordination, strictly according to the order of disclosure, safety measures, especially in the demolition of cable wind rope should pay attention to the stability of the frame.
3, the site responsible person should be based on the demolition plan, demolition order, the use of machinery and equipment and the specific circumstances of the scene, the preparation of safety technical disclosure, the content of the disclosure to be comprehensive, specific targeted.
4, good safety technical disclosure, the person in charge of the site according to the provisions of the class leader or all the workers, for writing and oral communication, clarifying the way of demolition, the demolition order, should pay attention to the use of mechanical equipment and on-site operation and specific requirements.
After the tests, AC (person in charge of the site, security officer), then (team leader) signed by both parties in written tests on disclosure after the operations team leader and its work of the staff to earnestly perform their duties, the demolition operation in accordance with the disclosure requirements.
5, before demolition, to the use of rope, mechanical equipment, support rod and so on, to meet the requirements can be used.
6, hoist the demolition work is strictly prohibited, down from a height to throw an object, remove the rod, etc. to clean up, placed in a prescribed position, and neatly.
7. When dismantling the windlass, the power must be disconnected first, and then the demolition work can be carried out after the inspection is correct.
8. Before removing cable wind rope or connecting rod, temporary cable wind rope or support should be set to ensure that the free height of the frame is not greater than two standard sections.
9. The stability measures of the two columns should be taken before the lifting of the Longmen tower.